The median new single-family house permit the City of Austin issued in 2026 took 48 days from the day the application was filed to the day the permit was issued. In 2025 the same figure was 60 days, and in 2023 it was 71. About one permit in seven this year, 14.4 percent, took more than 180 days.
That is a measure of the record, not a promise about any one project, and it has limits we spell out below. But if you are buying a house that is not built yet, or you have watched an empty lot for months, the number is a useful way to read what a permit date does and does not tell you.
Application to issue, year by year
| Year issued | Permits | Median days | Middle half (25th to 75th) | Issued within 30 days | Issued within 60 days | Took over 180 days |
|---|---|---|---|---|---|---|
| 2023 | 1,571 | 71 | 25 to 201 | 29.4% | 45.2% | 27.7% |
| 2024 | 1,804 | 51.5 | 25 to 96 | 33.6% | 56.0% | 13.9% |
| 2025 | 1,981 | 60 | 27 to 120 | 30.9% | 50.2% | 14.9% |
| 2026 | 1,881 | 48 | 24 to 94 | 35.8% | 61.3% | 14.4% |
Read the middle-half column as the usual range. In 2026, half of all new-house permits fell between 24 and 94 days, and the slowest tenth took 233 days or more. The 2026 median is the shortest of the four years, though 2024 is close. The percentages are our arithmetic on the city's dates.
The fall of 2025 was the slow stretch
| Quarter issued | Permits | Median days |
|---|---|---|
| 2025 Q1 | 514 | 57 |
| 2025 Q2 | 639 | 47 |
| 2025 Q3 | 461 | 56 |
| 2025 Q4 | 367 | 94 |
| 2026 Q1 | 518 | 65.5 |
| 2026 Q2 | 591 | 42 |
| 2026 Q3 | 552 | 43 |
| 2026 Q4 so far | 220 | 54 |
Permits issued from October through December 2025 had a median of 94 days, the longest quarter in the table. By the second quarter of 2026 it was 42. The City's Residential Plan Review page says that starting July 1, 2026 it is reducing review timelines for some project types, but the drop in these records came before that date, so we cannot tie the change to it.
Two kinds of lot, two very different clocks
| Jurisdiction | 2025 permits | 2025 median | 2026 permits | 2026 median |
|---|---|---|---|---|
| Austin full purpose | 1,316 | 78 | 1,377 | 57 |
| Austin limited purpose | 663 | 33 | 503 | 26 |
The feed labels each permit with a jurisdiction. The feed does not explain the difference, and we did not research the legal detail, so we will not guess at a cause. What the dates show is plain: limited-purpose permits are issued in about half the time. One 2025 permit was in the two-mile ETJ and one 2026 permit had no jurisdiction code, so they are in the year totals but not in this table. A buyer comparing two new builds may be comparing two different clocks, so ask which one applies.
The week of November 1
From Sunday, November 1 through Saturday, November 7, the feed shows 36 new single-family house building permits issued (the last one dated November 6). Their median was 45 days, 15 of the 36 (41.7 percent) were issued within 30 days, and 9 took more than 180 days. With 36 permits, a single slow application moves the percentages, so treat the week as a data point and not a trend. Last Sunday's piece covers the count of new houses by week and why a house carries four permits in the feed.
What this number is not
- It is not the City's review time. The City's Residential Plan Review page, which we read on November 8, lists 10 business days for new construction and additions per submittal, and 7 business days for an update. After the last reviewer approves, it says finalizing can take one to two days. Our figure runs from the application date to the issue date, so it also includes the time a set of plans spends back with the designer after comments, plus any wait for fees and activation.
- It only counts permits that were issued. An application still in review, or one withdrawn, is not in the table. Applications filed in the last few months are especially likely to be missing, because the slow ones have not been issued yet. That pulls the newest quarters down, and 2026 should be read as a floor on how long the whole group will take.
- It does not say when a house will be finished. A permit is permission to start. Construction, inspections and the certificate of occupancy come after.
- It says nothing about price or sales. The feed has no sale prices and nothing here uses MLS data.
What this means if you're buying, selling or living nearby
If you are buying a house that is not built yet. Ask the builder for the building permit number and look the permit up on the City's portal. The record shows the application date, the issue date and the status. A permit that is already issued puts a project months ahead of one that is still in review, and the table above shows how wide that range can be: a quarter of 2026 permits took 94 days or more, and the slowest tenth took 233 days or more. Do not read a closing date off a median.
If you are selling a house with an open or expired permit. Our earlier piece on expired home permits explains what a buyer inherits. Permit status is a record a buyer's agent can pull in a minute.
If you live near an empty lot. A building permit on an address does not mean trucks tomorrow. Permit history by address is free to look up, and our partner research site Zabalist keeps it in one place: search an address's permits on Zabalist.
How we counted
We used the City of Austin's open-data Issued Construction Permits feed as synced into our research database on November 8, 2026; the permits source shows a latest record dated November 6. We kept permit type BP (building permit), class R- 101 Single Family Houses and work class New, so a house is counted once, not four times with its electrical, mechanical and plumbing permits. Days are the issue date minus the application date, both from the feed, and we kept permits issued from January 1, 2023 through November 7, 2026. Every permit in that range has an application date on or before its issue date. The years combine all jurisdiction codes, matching the 1,845 year-to-date figure in last Sunday's piece. Medians and percentages are ours. The feed can add records after their issue date, so the newest rows may still change.